UPDATE ON THE VERNER MUNICIPAL BUILDING

February 5. 2019 

The Municipality has been working with Architects and Engineering firms on the construction of the Verner Municipal Building. With the progression of completed work thus far and the projected timeline for the remaining work, the project is anticipated to be completed by May 30, 2019.  

 

COMPLETED

✔ Temporary Shoring Installation 

✔ Designated Substance Survey   

 ✔ Investigation of the West Wall

 

REMAINING

Design – February 14 

Tender Period – February 15 -28

Council Award – March 5

Project Start (Demolition) - March 13

Project Completion –May 15

Commissioning + Project Close Out - May 30